Aysu General Contracting Co. Ltd
About Us

Aysu Contracting Company was established in 2008 and specializes in electrical power projects, including power generation and the manufacturing of spare parts and consumables for power plants.
The company also operates in the field of power transmission, undertaking projects such as the construction of 132/33 kV substations and the supply and installation of 132/33 kV mobile substations.
In the power distribution sector, the company is responsible for supplying, implementing, and installing 33/11 kV substations, as well as providing 33/11 kV mobile substations.
With extensive experience, our company specializes in supplying and installing power transmission towers and high-voltage cables, in addition to delivering and implementing compact substations of various capacities.
Furthermore, we have significant expertise in international trade and material procurement from leading global companies such as ABB, SIEMENS, and Schneider.
Additionally, we have expertise in building and infrastructure projects, having successfully executed numerous projects across various provinces of our esteemed country.
Our Work
number | Project name | Cost of work (dinar) | Start date | Actual achievement | Implementation level | Implementation period |
---|---|---|---|---|---|---|
1 | Electricity receipt to plot (77) opposite Tariq Company | 106,852,890 | 2008/6/3 | 2008/7/17 | good | 20 days |
2 | Electricity supply to Hussein Islam village / Laylan | 281,709,713 | 2008/6/3 | 2008/7/1 | good | 35 days |
3 | Expansion of the electricity network of the village of Dibek Tepe / Yayci | 65,044,159 | 2008/6/2 | 2008/6/16 | good | 20 days |
4 | Electricity receipt to plot (99) Part Two / Daquq | 287,923,520 | 2008/7/9 | 2008/8/4 | good | 30 days |
5 | Preparing 3 French circuit breakers | 64,500,000 | 2008/10/9 | 2008/10/13 | good | 10 days |
6 | Electricity connection to plot 328 behind the paper waste factory/center | 69,966,000 | 2009/1/19 | 2009/1/27 | good | 13 days |
7 | Purchase of French circuit breakers for the Al-Hawija power station | 63,000,000 | 2009/1/19 | 2009/1/20 | good | 3 days |
8 | Purchase of circuit breakers for the power station in Al-Hawija. | 125,000,000 | 2009/1/19 | 2009/3/7 | good | 45 days |
9 | Electricity connection to Block 3, Al-Askari District/Center | 44,596,000 | 2009/1/19 | 2009/1/28 | good | 10 days |
10 | Electricity connection to Block 3, Al-Askari District/Center | 44,596,000 | 2009/1/19 | 2009/1/28 | good | 10 days |
11 | Lighting the street of Al-Multaqa district with solar energy | 312,900,000 | 2009/6/25 | 2009/11/24 | good | 110 days |
12 | Lighting the main street from the Technical Institute to the end of Rahim Awa Street with solar energy / Center / C1 | 1,402,300,000 | 2009/2/25 | 2010/2/25 | good | 100 days |
13 | Lighting the main street with solar cells to the police station in Riyadh district | 177,700,000 | 2009/6/25 | 2009/12/1 | good | 110 days |
14 | Implementation and construction of a power station building within the Sayada complex / Kirkuk | 2,470,946,000 | 2011/11/15 | 2012/7/26 | good | 180 days |
15 | Construction and implementation of a power station in Tal Ali/Al-Hawij | 2,571,096,000 | 2011/11/26 | 2012/7/10 | good | 180 days |
16 | Construction of the Kirkuk Electricity Distribution Directorate building | 5,253,724,000 | 2014/1/5 | 2021/7/13 | good | 15 months |
number | Project name | Cost of work (dinar) | Implementation period | Start date | Completion rate | Implementation level |
---|---|---|---|---|---|---|
1 | Establishing the Shurao power station building, equipping and installing station equipment (11/33) kV with a capacity of (2*31.5) MVA, in addition to implementing a line of towers (33) kV/center | 4,048,640,000 | 210 days | 2013/9/25 | %100 | good |
number | Project name | Company Name | Contract amount (dinar) | Initial receipt date | Final receipt date |
---|---|---|---|---|---|
1 | Al-Ghadeer Village Secondary Station, voltage (33/11 Kv), capacity (2 * 31.5 mav), construction, equipment preparation, installation, operation and inspection | Esso and Sher Dora Contracting Companies | 8,166,974,000 | 2016/3/1 | 2019/5/7 |